Nukote Coating Systems verifiable project references cover a complete range of market segments, across all global regions. Many of our projects are high profile and complex, confirming our ability to deliver comprehensive solutions, which meet our client’s specific needs, in any global region and environment. The products and specifications we provide vary widely, depending on each projects unique requirements. The delivery of specific performance solutions is always consistent. The references included, represent a very small cross section of project profiles which were performed recently using Nukote products, specifications, applicators and equipment systems. Select the links below to view our reference sampling. For complete project references, case studies and more, please visit our Affiliates Page and acquire access to our complete database.
Iron Ore Rail Wagons

Iron Ore Rail Wagons

Location: Australia Reduced Carry Back (CB): Initial trials were implemented with the objective of sourcing a spray applied liner which would reduce load CB. (Carry back is defined as the amount of material that remains in the rail wagon
BWSS- Bangalore Sewerage Project Phase I

BWSS- Bangalore Sewerage Project Phase I

Project Overview: Nukote Coating Systems developed this projects specification working directly with the client, their consultants and a consortium of funding agencies. After two-years of review and approval process steps, Nukotes
BBraun Malaysia Reference

BBraun Malaysia Reference

LOCATION: BAYEN LEPAS, PENANG MALAYSIA CLIENT: B BRAUN MEDICAL INDUSTRIES SDN BHD INDUSTRY: POTABLE WATER TANK WATERPROOFING PURPOSE SYSTEMS: NUKOTE ST (PURE POLYUREA) 2MM APPLICATION TYPE: CONCRETE TANK COATED AREA: 1800 m² COMPLETION:
Western Power Poles

Western Power Poles

Location: Perth Western Australia Project Overview: Nukote Australia Pty. Ltd and Nukote Coating Systems International (USA), initiated trials with Koppers Wood Products (KOP NYSE $41.10) to develop a fire rated elastomeric coating to

Load more…

Kuala Lampur Metro- MRT Underground Station, Malaysia

Kuala Lampur Metro- MRT Underground Station, Malaysia

The project specified the application of Nukote ST (Pure Polyurea) over newly poured concrete. The client’s construction schedule required immediate coating after casting. Nukote HLT followed by Newkote EP Prime II was applied to eliminate
Parking Deck of Salvador Airport

Parking Deck of Salvador Airport

Project: Surface protection and waterproofing of the new parking deck at Salvador Airport Luis Eduardo Magalhães, Bahia, Brazil. Date: Nov 2015 – Mar 2016 A new parking deck level was included in the expansion project of the airport. This
Wilcox Tunnel Rehabilitation

Wilcox Tunnel Rehabilitation

Date: Nov 2015 – Mar 2016 Description: Nukote was engaged in this projectat the request of the clients consulting engineers. We visited the site on several occasions and worked directly in the specification development with the consultant
Hunts Point Compressor Station

Hunts Point Compressor Station

Location: New York Date: November 2015 Description: This project was initiated as atrial resulting from third party laboratory testing of Nukote Coating Systems products in 2012. Operations Technology Development (OTD) is an organization

Load more…

NUKOTE COATING SYSTEMS INTERNATIONAL has a long track record of projects, with references, ranging across all market segments, substrate types and environmental conditions. The products specified and their applied dry film thickness levels vary depending on the client's requirements, chemical concentrations present, ultraviolet exposures, ambient and process temperatures and substrates which the products will be applied to.

The following references represent a small cross section of project profiles which were performed recently. This page will be updated frequently. If you are looking for a specific application type that is not provided in the small sampling provided below, please contact us directly or contact your nearest Nukote affiliate for details.